Sunrise light on a grove of tufa towers emerging from the water of Mono Lake with soft green and dusty-red wild grasses in the foreground, Canada geese in the shallow water with reflections of the rocky towers, and desert hills in the distance.

Caltrans Hwy 395 rockfall project report #6

Caltrans-rockfall-update-graphic

Caltrans has released the sixth road report for the Lee Vining Rockfall Safety Project on Highway 395 along Mono Lake just north of Lee Vining.

Lee Vining Rockfall Safety project update #6


Capture 6aCapture 6c
Capture 6 b

Updates are also posted regularly on Twitter and Facebook.
Click here for all project updates and background.
Text from the official update is below.

Caltrans-rockfall-update-graphic

Project Update #6

Thursday, July 9, 2015

Project Purpose:

  • The project purpose is to minimize the rockfall from six cut slopes north of Lee Vining near Mono Lake to improve safety. The project includes a plant establishment program on all slopes to reduce erosion, establish healthy soil, and promote successful revegetation.
  • In addition, three of the slopes will receive anchored mesh to stabilize the slopes and reduce rockfall.

Timeline:

  • Slope #1 and slope #2 – work complete
  • Slope #5
    • Rock scaling is complete. Test anchors have been successfully drilled and tested.  The anchors will hold the anchored mesh and cable mesh in place.
    • Production anchor drilling is expected to be complete this week. In total, over 3,000 anchors are needed on the project.  For the northern portion of this slope the anchor work is complete and erosion control work is in progress.
    • Once all anchors have been drilled, erosion control work will begin in phases on the remaining slope, then the anchored mesh and cable netting will be installed.
  • Slope #6
    • The anchored mesh and cable netting has been placed.
    • Workers are now tightening the fasteners and contouring the mesh and netting to the slope.
    • The lower 8-10 feet will receive erosion control, then the mesh and netting will be fastened and contoured to this part of the slope.

Road Closures:

  • 1-hour closures have not been scheduled. As soon as more specific information on these closures is available another project update will be distributed.  1-hour full closures will be from 6 am to 7 am.
  • Delays during construction will mostly be standard up-to-20 minute delays with one-way reversing traffic control. The temporary signal uses detection technology to minimize delays.

Construction began May 4 and is planned to continue through fall 2015.  Construction may also be required in spring/summer 2016.

More information:
— Cedrik Zemitis, Caltrans Project Manager, 760-872-5250 or by email. If you would like to be added to the email list for project updates, email Cedrik Zemitis.
— Florene Trainor, Caltrans Public Information Officer, 760-872-5235 or by email.
— For general State highway information: 1-800-427-ROAD (7623) or the website.