Caltrans Rockfall Project work suspended for the rest of the year; no more traffic delays north of Lee Vining

August 14th, 2015 by Lisa, Eastern Sierra Policy Director
Share...Share on Facebook0Tweet about this on TwitterShare on Google+0Pin on Pinterest0Share on LinkedIn0Share on Reddit0Share on Tumblr0Email this to someone

As of Wednesday, August 12, the contractor completed Stage 1 of the Lee Vining Rockfall Safety Project and all equipment, including one-lane traffic control signals and barricades, have been removed from the project site. Since early May, Highway 395 north of Lee Vining had been reduced to one-lane to allow the crew room to maneuver—scaling rocks off the slopes, installing anchored mesh, and applying blends of soil amendments and seeds for successful revegetation.

The completed work on Slope 6 of the Lee Vining Rockfall Safety Project: rocks scaled away, anchored mesh installed, and mulch, soil amendments, and seeds applied. Photo by Sandra Noll.

The completed work on Slope 6 of the Lee Vining Rockfall Safety Project: rocks scaled away, anchored mesh installed, and mulch, soil amendments, and seeds applied. Photo by Sandra Noll.

Stage 1 is completed and four of the six project slopes are done. Stage 2 will address slopes 3 and 4 and will begin in spring 2016 as soon as weather conditions allow for work.

The project was originally planned to take two seasons to complete and although it appeared for a while that the entire project would be finished this year, the contractor is playing it safe by not transitioning to the next phase and allowing an entire season for Stage 2. Traffic delays are done for now and all of us—including the contractor—will know what to expect next spring.

Tags: , , , , , , , , , ,


2 Responses to “Caltrans Rockfall Project work suspended for the rest of the year; no more traffic delays north of Lee Vining”

  1. avatar Jean Brocklebank Says:

    Thanks for the update. We did not find the project delays difficult at all. We’ll be back next season and adapt to the work. A stay in Lee Vining and being at Mono Lake is far too important to us to allow such discomfort to ruin our annual life’s batteries recharge!

  2. avatar Raymond R. White Says:

    “and applying … for successful revegetation.” might be premature.